Japan seeks comment by Dec 24 on how carbon costs enter baseload power price caps

Japan's energy agency has opened a month-long consultation on a revised baseload market guideline that spells out how emissions-trading costs and decarbonisation-auction plants feed into the price ceiling large generators may offer.

By Tokyo Brief DeskNov 27, 2026, 01:23 JST3 min read
Stylised illustration of power plant equipment and transmission pylons beside a stack of price-ceiling bars representing a wholesale power offer cap.

The Agency for Natural Resources and Energy (ANRE) opened a public comment on 25 November on a draft revision of the baseload market guideline. The guideline governs how large generators offer coal, nuclear, run-of-river hydro and geothermal power to retailers through the wholesale exchange. Comments are accepted until 24 December 2026, and the consultation is a voluntary one rather than a procedure required under the Administrative Procedure Act.

A fix-up to an October rewrite

The guideline was last revised on 5 October 2026, after working-group discussion of two items: how winners of the long-term decarbonisation power auction are treated in the price ceiling, and how emissions-trading costs are calculated. ANRE says passages were identified that should be reviewed for proper operation and clearer interpretation. The working group on the electricity business environment approved the changes at its fifth meeting on 18 November.

The notice does not itemise what changed from the October text, and the draft leaves its own revision date blank. Readers will need to compare the two versions themselves.

How the price ceiling is built

The draft says the cap on offers should rest on the average generation cost of a covered company's baseload plants: the combined costs, plus cost equivalents for auction-winning plants, divided by expected generation, worked out broadly along the lines of the rules for deemed retailers' regulated tariffs. It applies to companies with at least 5 million kW of generation nationwide, their parents, or generators in which they hold at least one-third.

For plants that won the long-term decarbonisation auction and are within the scheme period, the draft sets the cost equivalent as a market-price-based unit price multiplied by expected output. That unit price adds the simple average day-ahead spot price in the plant's area over the prior one year (two years for two-year trades) to the average price in a second market the draft names. A generator may instead use the plant's variable costs not supported by capacity revenue, if those exceed the cost equivalent calculated that way.

The carbon line

The emissions-trading cost starts from a company's expected direct CO2 emissions across its whole generation business, less its allowances. If the result is zero or below, the cost is zero, and surplus allowances committed to future surrender or to further decarbonisation investment are kept out of the ceiling. A positive gap is apportioned across generating units in proportion to each unit's excess over its benchmark allowance; the shares assigned to coal units are added up and multiplied by an expected allowance price.

Before allowance trading begins, that price is the midpoint of the year's upper and lower price limits. The draft says those limits can be set using the 3% annual rise built into them and expected inflation. For two-year trades, each delivery year's cost is calculated and summed.

Oversight

The draft expects the Electric Power and Gas Market Surveillance Commission to check offered volumes and ask for cap calculations in the year before delivery, and to compare actual generation costs and output with forecasts in the year after. Where explanations are not objectively reasonable, it says the commission will issue a warning. Separately, it says that if a generator is seen to fail to offer proper volumes, miscalculate its cap or offer at improper prices, the company name and the conduct may be published after due process. The draft also says ending the market is desirable once the wholesale market is functioning and competition is sufficiently active, without saying when.

Comments must be in Japanese on the prescribed form and sent through the e-Gov portal, by post or by email. ANRE says it will not reply to individual comments and that submissions may be published, minus names and contact details.