LNG-only power projects that win the fourth long-term decarbonized power auction would be able to choose a fixed refund, instead of returning a share of their actual market profit, under draft rules from the Agency for Natural Resources and Energy. The agency opened a public consultation on the draft on 24 November 2026 and takes comments until 23 December 2026.
The choice on offer
Under the current design, winners receive capacity payments covering their fixed costs and return about 90% of their actual other-market profit to OCCTO, the market administrator. The draft keeps that route and adds a second one for LNG-only plants: a refund fixed in advance for five or ten years.
| Option | Period | Refund to OCCTO |
|---|---|---|
| Actual-based (current) | Support period | About 90% of actual other-market profit |
| Fixed, five years | 5 years | ¥9,900 per kW a year |
| Fixed, ten years | 10 years | ¥8,300 per kW a year |
The choice is made once, in the year the plant starts supplying capacity. Operators who pick the actual-based route cannot later move to a fixed refund. Those who pick a fixed refund can choose again after each five- or ten-year period, at whatever level applies then. The fixed figures are adjusted each year by core consumer prices. The two quoted rates apply to plants starting supply by fiscal 2034 (the year to March 2035); the agency plans to reassess the scheme and the level in fiscal 2031 and to set rates for plants that start supply or choose again from fiscal 2035.
Bids are still priced on full fixed cost and compete in the same quota as plants staying on the current route. The rules that stop winners from selling cheaply to affiliated retailers to avoid a refund would not apply while a fixed refund runs. Revenue from other uses of supported assets, such as third-party use of an LNG terminal, would still be refunded on actuals.
Where the numbers come from
The agency's stated aim is to leave LNG-only operators room to earn above the refund, so they are willing to take on the surplus-fuel risk of long-term LNG contracts. A fixed refund removes the step at which a profit triggers a clawback.
The levels rest on spot-price averages over the past five and ten years, excluding trading intervals priced at ¥0.01 per kWh. The LNG fuel cost uses the annual average JLC price, chosen because the model assumes long-term contracts. The utilisation assumption is about 60% for five years and about 52% for ten. The agency chose national system prices over area prices.
A working-group meeting on 14 July had been shown ¥8,000 per kW a year. Several members said the basis was too thin, and the group reconsidered the refund level at its 7 October meeting. The draft's two figures are both above ¥8,000. The guideline draft footnotes also say the fixed-refund level and how it is set remain under council review and will be reflected in the guideline. The draft is neither a final rule nor an awarded term.
Utilisation floors for solar, wind and hydro
For solar, wind and run-of-river hydro, the draft would lower most of the minimum annual capacity factors that winners must meet. These currently follow the figures assumed in feed-in tariff and feed-in premium (FIT/FIP) pricing: 18.3% for solar, 29.1% for onshore wind, 39.3% for offshore wind and 44.8% for run-of-river hydro. Developers argued that falling slightly below an average should not trigger a penalty.
The draft would set the floor at the lowest annual average published over the past ten years: 14.8% for solar, 24.5% for onshore wind, 25.2% for offshore wind and 51.0% for run-of-river hydro. The run-of-river floor therefore rises. The draft says no past winner is subject to this requirement.
Other round-four terms for LNG-only plants
The draft seeks 6 million kW of LNG-only capacity in the fourth round. It sets separate price caps for projects that need a new LNG terminal and those that do not, raising the cap from ¥55,000 per kW a year to as much as ¥92,000 for projects that include terminal construction. The deadline to start supply moves to 11 years, or 7 where environmental assessment is complete or not required, and the support period is capped at 30 years.
Comments go in Japanese through e-Gov, by post or by email to the agency's power infrastructure division by 23 December.