Tokyo Electric Power says the construction schedule for safety facilities at Kashiwazaki-Kariwa units 6 and 7 needs review after its contractor sought changes and uneven concrete was found in part of a main structure; it has not announced a new date.

Concrete formwork and steel reinforcement at a power plant construction site beside an empty schedule board

Tokyo Electric Power Company Holdings has concluded that the construction schedule for the specified severe accident response facilities at units 6 and 7 of its Kashiwazaki-Kariwa nuclear plant needs review, and has not yet announced a replacement timetable. The company said so in a notice dated 26 November 2026.

What TEPCO said changed

TEPCO had earlier announced a completion timing for the facilities in a 27 February 2025 notice about submitting a construction plan change notification tied to the reactor installation permit. The new notice gives two reasons for reopening that schedule.

First, the construction company building the main structures reported that the work content needs to be reviewed and that it wants to change the schedule. Second, TEPCO confirmed that in part of the main structures, construction problems left the concrete finish uneven. TEPCO said these points, among others, led it to conclude a schedule review is needed.

What the facilities are

The notice describes the specified severe accident response facilities as installations meant to prevent damage to the reactor containment vessel when large-scale damage from a deliberate aircraft crash or similar event leaves equipment unusable over a wide area. They provide functions such as depressurising the reactor pressure vessel and injecting water, and depressurising and cooling the containment vessel.

What is not yet known

TEPCO said it will consider the schedule review and announce the new construction timetable once it is decided. The notice gives no revised completion date and does not quantify the length of any change. It does not address reactor operations, so no restart or regulatory consequence can be read from it.

TEPCO added that it will keep working to improve safety and reliability in light of lessons from the Fukushima Daiichi accident. The next disclosure to watch is the announcement of the new construction schedule.