Tokyu Construction and Max Infrastructure Limited have won the CP04 package on Dhaka's MRT Line 1, valued at about ¥76.4bn, according to the contractor's interim results presentation of 19 November. The deck calls it Bangladesh's first underground metro mainline construction project.
What the package covers
CP04 comprises four underground stations and two single-track tunnels of about 3.0km. Line 1 as a whole has two routes: an airport line with 12 underground stations and a second line with seven elevated stations.
The contract signing ceremony took place in Dhaka on 4 November 2026. The deck gives a construction period of 60 months from around April 2027 and a planned completion in 2032.
Who is doing the work
The contract is held by a joint venture of Tokyu Construction and Max Infrastructure Limited, with Tokyu as sponsor. The ¥76.4bn is the package value as the deck gives it, in yen terms. The deck does not split it between the partners, so it should not be read as Tokyu's own revenue.
Tokyu says it will apply Japanese techniques, naming one-pass joints for tunnel segments. It describes the package as its fourth project in Bangladesh, after two vehicle-depot site works and two sections of the Matarbari port access road, which are under construction.
Place in the results deck
The award sits in the international business section of a deck that also lays out the group's raised full-year outlook. Tokyu now forecasts operating profit of ¥18.0bn for the year ending March 2027, up ¥1.5bn from its initial forecast. Interim operating profit was ¥5.63bn.
The 2032 date is the deck's planned completion, not a guarantee.