Takeuchi Mfg Pushes New Factory Opening to 2029 as Project Cost Rises to About ¥24.6bn
Takeuchi Mfg says a construction-labor shortage pushed its new factory's opening from January 2028 to May 2029, and rising building costs plus spec changes lifted the project's budget from about ¥18.0bn to about ¥24.6bn, with output capacity unchanged.