Kaihan, the Tokyo-listed company (code 3133), has withdrawn the completion dates for the four first-phase projects in its Nepal hydropower venture. Its board approved the revised plan at an extraordinary meeting on 20 November 2026, citing delayed financing and flood damage in Nepal.
Four projects now undated
The four projects (5.5MW, 8.3MW, 9.1MW and 13.7MW of planned capacity) previously carried completion dates between January and May 2027. All four now read "undecided".
| Project | Planned capacity (MW) | Previously announced | Current plan |
|---|---|---|---|
| Dupcheshwor Mahadev Hydro | 5.5 | January 2027 | Undecided |
| Water Energy Solution | 8.3 | May 2027 | Undecided |
| Super Glelamdi Khole Hydro power | 9.1 | May 2027 | Undecided |
| Betrawati Hydro Electric | 13.7 | April 2027 | Undecided |
The company said its 26 August schedule was the shortest possible plan and assumed funding would be complete by November 2026. Funding is "significantly behind" the original assumption and the money needed for the project has not been secured. Kaihan said the financing it plans under its 20 November announcement of a third-party share allotment and new warrants does not complete the funding for its Nepal investment, so it left the dates undecided. It said it will announce new progress as it occurs.
Floods hit site preparation
The Nepal army is due to carry out the mountain-site preparation work for the plant construction. Kaihan said the army is giving priority to flood recovery, which affects when it can start work on the project's sites, so the local construction schedule also needs revising.
Later phases under review
The four undated projects cover the first phase only. For the second and third phases, Kaihan said it will consider transferring rights to local operators or cancelling projects, given its financing position. It still lists 2029 and 2033 completion dates, but said they were carried over from the earlier plan and that it has not decided to proceed as listed.
How the money is meant to arrive
For the first phase, Kaihan plans to rely mainly on advances from its local partner, SURYA MAINA HOLDING PVT LTD, and on borrowing. It said it will confirm and discuss the costs, amounts, timing and settlement method of the advances, and confirm and review the borrower, lender, amount, timing and conditions of the borrowing. Timing and conditions are not yet fixed. As of the disclosure date, the partner's advance on Kaihan's share was about ¥100mn, for site-preparation costs on the first project. If funds do not arrive as planned, construction, completion and revenue timing may be affected.
Revenue guide
The financial plan still assumes first-phase sales from March 2027 and ¥19mn of project revenue in the year to March 2027. Kaihan said that figure is not fixed, and that the date power sales begin is still being confirmed, including post-completion testing and grid connection. The plan does not reflect the outcome of the later-phase review, and the effect on consolidated results is still being assessed.
