Datasection cuts its revenue forecast to ¥17.29bn and rests it on one operating project

Datasection's revised outlook rests on one operating project, with sales guidance cut from ¥162.19bn to ¥17.29bn after a ¥3.07bn special loss on cancelled Australian capacity and an unextended exclusive financing agreement.

By Tokyo Brief DeskNov 26, 2026, 19:20 JST3 min readDatasection Inc.3905
Rows of GPU server racks in a data hall with power cabling overhead and an empty rack bay in the foreground.

Datasection's revised outlook for the year to March 2027 assumes a single operating AI-infrastructure project. Sales guidance falls to ¥17.29bn from ¥162.19bn in the May forecast, and the net result moves to a ¥1.48bn loss from a forecast profit of ¥8.70bn. The earnings presentation, used at the company's November 16 results briefing, says the original forecast included projects A to C plus additional services to the same customer. Earlier Tokyo Brief coverage

What the forecast now assumes

The revised figures assume only the first operating project runs. Datasection says the revision and its internal estimates include storage and CPU server rental to the offtaker, the customer buying the capacity.

Full-year forecast, year to March 2027
Previous forecast published May 15, 2026; revised forecast assumes only the first operating project. Source figures are in ¥mn.
MetricPrevious forecastRevised forecast
Sales¥162.19bn¥17.29bn
Operating profit¥24.82bn¥4.92bn
Adjusted EBITDA¥58.19bn¥10.20bn
Ordinary profit¥12.54bn¥2.46bn
Net profit attributable to parent¥8.70bn profit¥1.48bn loss

For the following year, the company gave two rough internal estimates: one with only the first operating project and one with all three projects at full capacity. These are internal scenarios and not guidance.

A profitable operation, a loss below the line

Interim sales were ¥6.69bn, up 283.4%, and operating profit was ¥3.02bn against a ¥1.37bn loss a year earlier. The parent's net result was a ¥2.35bn loss. Datasection attributes that to non-operating costs, including interest and foreign-exchange losses, and to a ¥3.07bn special loss.

The July to September quarter alone was weaker: sales of ¥366mn and an operating loss of ¥1.83bn. The deck cites the cancellation of an additional-order project, a delay in bringing a data-centre project to full operation, and depreciation on leased assets.

Australia and the financing agreement that ended

The special loss comes from the Australian business, which spans two sites totalling 160MW (60MW and 100MW). Datasection cancelled an initial 20MW block it had contracted early at the 60MW site, citing a change to its original plan. The charge is ¥2.75bn of lease termination loss and a ¥314mn provision for the communications-line fees that run on after cancellation. Datasection says the charge does not touch operating profit or adjusted EBITDA, and that it plans to take another 20MW block at the same site.

On financing, an exclusive arrangement agreement signed on May 11 with a global investment firm managing $100bn expired on November 11, and Datasection decided not to extend it. The agreement aimed to raise $500mn to $1bn for GPU servers. For the operating project, a different financial institution has cleared its loan screening and approved a loan in principle. The loan agreement is still to be signed. Separately, the 23rd stock acquisition rights expired on October 19 with 21,394,200 shares exercised (48.62% of the total), raising ¥27.14bn. Datasection said at the time that this was about ¥28.6bn below plan.

The contract behind the revised number

The operating project rests on a contract announced on September 18, worth ¥139.92bn over five years. It runs for three years with a customer option to extend by up to two. Service began in October, as scheduled. The customer is a US-headquartered AI infrastructure platform provider, and its name is withheld under a non-disclosure obligation. Datasection expects storage-server provision to add about $30mn a year, around $150mn over five years.

Of 20,000 Blackwell-generation GPUs secured across three projects, 4,616 had been delivered by November. The remaining 2,000 for the first project are due by mid-December, and the 10,000 for the third can ship two to three weeks after ordering.