Daihatsu Infinearth order backlog reaches ¥142.8bn after Himeji expansion

The marine-engine maker's order book stood at ¥142.8bn at the half-year end, about 41.3% above a year earlier, with the container-ship backlog the standout after the Himeji plant extension began operating in February.

By Tokyo Brief DeskNov 19, 2026, 19:51 JST2 min readDAIHATSU INFINEARTH MFG.CO.,LTD.6023
Large marine engines lined up at test-run bays in a factory, beside three rising stacked bars representing a growing order book.

Daihatsu Infinearth's order backlog reached ¥142.8bn at the end of the first half of the year to March 2027, about 41.3% above a year earlier, according to its interim results presentation. The marine-engine maker attributes the rise to the expanded Himeji plant.

Capacity already added

The Himeji extension was completed at the end of 2025 and began operating in February 2026. Test-run facilities rose from 10 to 18 units: one started in February, and the company says the other seven were running in the first half of the current fiscal year, as planned. It expects Himeji unit sales to reach about 1.8 times the level of the year to March 2026.

What is in the order book

The backlog stood at ¥113.5bn at the end of the year to March 2026 and ¥101.1bn at the previous half-year end. The presentation singles out container ships, whose order backlog was about 2.4 times a year earlier. Dual-fuel engines make up 27% of the backlog, large engines 29% and small and medium engines 44%.

The interim numbers carry the same theme. Sales rose 20.6% to ¥50.1bn, operating profit rose 65.9% to ¥4.1bn and net profit rose 28.5% to ¥2.7bn. Engines sold in the half totalled 438 units, against 392 a year earlier. The full-year plan, raised on July 31, is ¥107bn in sales and ¥10bn in operating profit.

Still to come

The first methanol dual-fuel engine is scheduled to ship in 2027, and 12 units for three ships are already on order, to be built at Himeji. The ammonia dual-fuel engine is targeted for commercial release in 2028, with real-engine testing at the Moriyama plant having begun in September 2026.