Shibuya West approval sets outline of Tokyo Tatemono's planned ¥270bn purchase as Daiwa Office joins for floor rights

Tokyo Tatemono plans to acquire about ¥270bn of land and buildings in the Shibuya 2-chome West redevelopment after the governor approved the rights-conversion plan, while Daiwa Office Investment plans to take new office floors, with completion scheduled for 2035.

Stylised cross-section of a tall mixed-use tower with some floors shaded to show ownership shares, a bus terminal at its base and construction cranes along a timeline.

The Tokyo governor approved the rights-conversion plan for the Shibuya 2-chome West redevelopment on 24 November. Tokyo Tatemono said the approval determined the outline of the assets it plans to acquire. Daiwa Office Investment announced alongside the approval that it will join the project and take new floors rather than sell.

Tokyo Tatemono: a planned ¥270bn purchase

Tokyo Tatemono is both a rights holder and a participating member of the Shibuya 2-chome West redevelopment association. It said it decided on 24 November to acquire part of the land and buildings from that association, for a planned amount of about ¥270bn. The figure is the company's planned acquisition price, not a project cost and not a completed purchase. The notice does not say how the amount splits between land and buildings.

The company gives main construction as running from 2029 to 2035, and says the acquisition was already built into the consolidated forecast for the year to December 2026 that it published on 6 August. The forecast is unchanged. The notice adds that the plan may change after further discussions.

The project the rights attach to

The association's redevelopment covers two blocks. Block B is the large one: a site of about 12,770 square metres, about 235,000 square metres of floor space, three floors below ground and 38 above, and a height of about 192 metres. Planned uses are offices, shops, a hotel, a talent-development facility and a bus terminal. Block A is a five-storey shop building of about 46 metres. Daiwa Office's disclosure says a separate voluntary rebuilding scheme on a third block, C, completes a combined project with a site of about 18,700 square metres and about 305,800 square metres of floor space.

Daiwa Office: floors instead of a sale

Daiwa Office Investment owns the Daiwa Shibuya Miyamasuzaka Building in block A. It said it decided to join the project and plans to acquire "rights floors", meaning floors in the rebuilt structure that replace its old land and building rights under the Urban Redevelopment Act, through the rights conversion. It expects about 5,622.36 square metres of office space (planned) in the block B tower. The REIT's rationale is that holding for the medium to long term serves unitholders better than selling now and realising the unrealised gain.

The rights conversion date is planned for 1 December 2026. During construction the association is due to pay compensation under the same law, and Daiwa Office expects to keep profitability close to the building's recent level. It rates the effect on its November 2026 and May 2027 periods as minor and left its forecasts unchanged.

Valuations, with caveats

A research report by the Japan Real Estate Institute puts the property at ¥21.8bn as of 1 May 2026. That figure assumes the new building is finished and lettable, and Daiwa Office says it does not guarantee a future appraisal. The end-of-May 2026 appraisal of ¥13.1bn did not factor in the project. The supplementary deck puts book value at about ¥7.0bn and says it does not change on rights conversion. The report's operating revenue and cost lines are undisclosed because the association has not consented.

Completion is scheduled for 2035, with main construction starting in 2029. Tokyo Tatemono's notice says the content may change after further discussions. Daiwa Office says the schedule is current and may change with the project's progress.