Weekday Japan business intelligence for finance professionals.

Join the list
Tokyo Brief東 京 ブ リ ー フ

Japan's day, wrapped and delivered by morning.

Article

Tomakomai AI data-center project commits ¥3.94bn to a 66kV substation

Environmental Friendly Holdings said its subsidiary AI Tech Tomakomai has signed a ¥3.94bn tax-included contract with Yurtec to build a 66kV substation for the Tomakomai AI data-centre site in Hokkaido. Construction starts on July 1, 2026 and completion is scheduled for Dec. 13, 2027, with the company describing the asset as the route from an initial 10MW plan toward a 50MW receiving-capacity target. Funding is supposed to come from internal cash, retargeted equity proceeds, warrant exercises and possibly bank borrowing. The catch is familiar: part of the money depends on future warrant exercises, so the power plan is solidifying faster than the financing certainty.

Jun 19, 20263 min read
Editorial illustration of high-voltage substation equipment beside modular data-center units at an industrial site.

Before Environmental Friendly Holdings can sell AI capacity in Tomakomai, it has to secure serious power. The company said its subsidiary AI Tech Tomakomai will build a 66kV extra-high-voltage substation at the Hokkaido site under a ¥3.94bn, tax-included contract with Yurtec. Management describes the asset as core infrastructure for the project, a step meant to move the site from an initial 10MW setup to a longer-term 50MW receiving-capacity plan.

Tomakomai power build at a glance
Based on Environmental Friendly Holdings' June 19 disclosures. Wider project costs remain only partly disclosed.
ItemDetail
Project asset66kV extra-high-voltage substation equipment for the Tomakomai AI data center
LocationTomakomai, Hokkaido
ContractorYurtec Corporation
Contract value¥3.94bn, tax included
Construction startJuly 1, 2026
Completion and handoverDec. 13, 2027
Initial operating plan10MW, with power receipt from July 2026 and operations targeted for October 2026
Longer-term planSwitch phase one to extra-high-voltage receiving and expand toward 50MW
Funding planInternal funds, warrant-exercise proceeds, and possible bank borrowing

What the contract actually buys

The fixed-asset purchase is not a vague electrical placeholder. Environmental Friendly says it covers 66kV receiving equipment, a main transformer, gas-insulated switchgear, protection and control equipment, extra-high-voltage cable, grounding, and related civil and building works at the Tomakomai site. Construction is scheduled to start on July 1, 2026, with completion and handover set for Dec. 13, 2027.

That matters because AI Tech Tomakomai plans to start phase one at 10MW, begin receiving power in July 2026, and target business operations from October 2026 using high-voltage receiving equipment. Once the new substation is finished, the company says it plans to switch that first phase to extra-high-voltage receiving and then add equipment in stages toward 50MW.

How management says it will pay

Environmental Friendly says the substation will be funded with internal funds and money raised through warrant exercises, while bank borrowing is also under consideration. A separate same-day financing notice makes that more specific. It says previously raised capital is being redirected toward the Tomakomai project, including the substation and ¥2.94bn of land-preparation and foundation work for the first phase.

In that filing, the company says ¥1.147bn of still-unallocated proceeds from its 21st warrants will go toward the substation, and that ¥140mn from shares issued in May 2025 plus ¥128mn already raised via 22nd warrants will also help cover the first substation payment. It also says a planned ¥437mn from the 22nd warrants is earmarked for phase-one site works, and that the 23rd warrants, which had not been exercised as of June 19, were retargeted toward the AI data-center project as well.

What remains unclear

The headline ¥3.94bn does not fund the whole build-out. Environmental Friendly says the Yurtec contract is only one part of the second-phase investment plan, and it also says additional first-phase works may be needed after technical review. Those add-ons have not been fixed in scope or price, and no decision has been made on awarding them.

Nor is the financing fully settled. Part of the plan depends on future warrant exercises, while borrowing remains under consideration. In the funding-change filing, the company also notes that if warrant exercises do not progress as expected, it may seek alternative financing. For now, the Tomakomai build is less a story about server racks than about whether the power infrastructure and funding line up on time.